Major investment in 2025
Weeks 7-8
Weeks 7-8
Riggtech has now successfully installed the supply and return pipes in the ground, while Dalafrakt has ensured that the area around the children's pool has been restored.
EdGyr has been working flat out, laying out cellular plastic and reinforcement mats – now the children's pool slab is seamlessly integrated with the impressive wall of the attraction pool. Next week will be an exciting milestone when the casting begins!
At the same time, the ground between the pool and the water treatment plant has thawed, and excavation work is now in full swing. Soon, pipe laying can begin and be connected to the water treatment plant—another step closer to completion!