Major investment in 2025
Weeks 4-5
Weeks 4-5
During week 4, we cast all the wall sections in the attraction pool, and demolition of the forms began during week 5. The return pipes are being installed behind the large wall, and the large pipes strandpoolen be put in place at strandpoolen . The old pool system under the kiosk is now completely gone.
As planned, an order has now been placed for twelve large deciduous trees to create a pleasant environment around the pools. Groundwork and pipe work has been ongoing all week, and next week the backfilling of the slope by the children's pool will begin.